Regulations
- Forest Practices Code of BC ActSTILLWATER PILOT PROJECT REGULATION
B.C. Reg. 96/01, Deposited April 5, 2001
O.C. 0427/01, effective April 5, 2001 consolidated to August 5, 2003
PART 1 - INTERPRETATION
PART 2 - BALANCING COMPETING VALUES AND
INTERESTS
PART 3 - FOREST STEWARDSHIP PLAN, CUTTING
PERMIT, OPERATIONAL INFORMATION MAP AND SITE PLAN
PART 4 - FOREST PRACTICES IN THE STILLWATER AREA
PART 5 - PUBLIC PARTICIPATION IN THE
STILLWATER PILOT PROJECT
PART 6 - APPROVAL AND TERM OF FOREST
STEWARDSHIP PLAN
PART 7 - FOREST STEWARDSHIP PLAN CONTENT
PART 8 - REPORTS AND RECORDS
PART 9 - MONITORING AND EVALUATION
PART 10 - COMPLIANCE AND ENFORCEMENT
PART 11 - CANCELLATION OF STILLWATER
PILOT PROJECT
SCHEDULE A
SCHEDULE B
- 28.(1) The licensee must notify the district manager before harvesting in an area
for which a cutting permit was issued under Division 2 of Part 3 if more than 3 years have
passed since the cutting permit was issued.
(2) The licensee must not harvest in an area that is within a community watershed if the
result of the terrain stability assessment indicates that the area is subject to a high
likelihood of landslides.
(3) The licensee must not clearcut an area that is within a community watershed if the
result of the terrain stability field assessment indicates that the area is subject to a
moderate likelihood of landslides with a high risk of landslide debris entering directly
into steams, unless the terrain stability field assessment documents the assessor's
opinion that, based on the assessment, the assessor has reasonable grounds to believe that
clearcutting the area will not significantly increase the risk of a landslide.
(4) The licensee must not clearcut an area that is outside a community watershed if the
result of the terrain stability field assessment indicates that the area is subject to a
high likelihood of landslides, unless the terrain stability field assessment documents the
assessor's opinion that, based on the assessment, the assessor has reasonable grounds to
believe that clearcutting the area will not significantly increase the risk of a landslide
and that there is a low likelihood of landslide debris
- (a) entering into a fish stream or a perennial stream that is a direct tributary to a
fish stream, or
(b) causing damage to private property or public utilities, including but not limited to
roads, bridges, transmission lines, pipelines, recreation sites or any other similar
structures.
(5) The licensee must not construct an excavated or bladed trail on an area that is
outside a community watershed if the result of the terrain stability field assessment
indicates that the area is subject to a high likelihood of landslides.
(6) The licensee must not construct an excavated or bladed trail on an area that is inside
or outside a community watershed if the result of the terrain stability field assessment
indicates that the area is subject to a moderate likelihood of landslides, unless the
assessment documents the assessor's opinion that, based on the assessment, the assessor
has reasonable grounds to believe that
- (a) the excavated or bladed trail can be located, constructed and rehabilitated in a
manner that will not significantly increase the risk of landslides, and
(b) there is a low likelihood of landslide debris
- (i) entering into a perennial stream in a community watershed, a fish stream or a
perennial stream that is a direct tributary to a fish stream, or
(ii) causing damage to private property or public utilities, including but not limited to
roads, bridges, transmission lines, pipelines, recreation sites, or any other similar
structures.
(7) The licensee must not yard or skid timber through or over a stream unless the
yarding or skidding is authorized by a forest stewardship plan or by the district manager
or designated environment official, in writing, with or without conditions.
- 29.For areas harvested under a forest stewardship plan, the licensee must
establish, in accordance with this regulation and the forest stewardship plan, a free
growing stand on the area, except for the portion of the area that
- (a) is occupied by permanent access structures, or
(b) in its natural state is not capable of supporting a stand of trees that meets the
stocking requirements specified in the forest stewardship plan.
- 30.For the purposes of section 96 (1) (g) (iii) of the Act, the licensee, without
obtaining a cutting permit, is authorized to cut, damage or destroy Crown timber in the
course of carrying out stand management activities in accordance with the strategies and
measurable targets in a forest stewardship plan.
- 31.Any forest practices carried out in the Stillwater area under a forest
stewardship plan must be carried out in a manner consistent with the forest stewardship
plan and any field variance referred to in section 32.
- 32.(1) In this section, "field variance" means a variance from a
provision of a forest stewardship plan.
(2) If the licensee wishes to change the strategies and targets in a forest stewardship
plan, the licensee must submit an application for a field variance to the district manager
or designated environment official.
(3) An application for a field variance must be signed and sealed by a professional
forester.
(4) The district manager or the designated environment official may approve a field
variance to a forest stewardship plan if the district manager or the designated
environment official determines that the field variance
- (a) otherwise meets the requirements of the Act and the regulations,
(b) will adequately manage and conserve the forest resources for the area to which it
applies, and
(c) does not materially change the forest stewardship plan.
- 33.(1) For the purposes of this section, sections 55 and 56 of the Act apply to
the licensee as if it were the holder of a road permit.
(2) A person other than the licensee who has a right to harvest timber in the Stillwater
area may apply to the district manager under section 115 of the Forest Act for a
road use permit for a road constructed or used by the licensee under a forest stewardship
plan.
(3) Subject to section 81 of the Forest Act the district manager must grant a
road use permit to an applicant under subsection (2) if the district manager is satisfied
that the use of the road by that person will
- (a) not adversely affect authorized users of the road, or
(b) compromise the forest stewardship plan.
(4) A person other than a person referred to in subsection (2) who wishes to use a road
constructed or used by the licensee under a forest stewardship plan for an industrial
purpose, may apply to the district manager under section 117 of the Forest Act
for a road use permit.
(5) The district manager may grant to an applicant under subsection (4) a road use permit
if the district manager is satisfied that the use of the road by that person will not
- (a) cause unnecessary disturbance to the natural environment,
(b) adversely affect authorized users of the road, or
(c) compromise a forest stewardship plan.
(6) A road constructed, modified or maintained by the licensee in the Stillwater area
may be used for purposes other than those listed in section 54 (1) and (2) of the Act by
any person without charge, in accordance with the conditions set out in section 55 of the
Act.
(7) The licensee must not require payment from a person who uses the road except in
accordance with the conditions set out in section 56 of the Act.
- 34.(1) Subject to subsection (3), the licensee must maintain all roads
constructed or used under the authority of a forest stewardship plan until
- (a) the road is temporarily or permanently deactivated,
(b) a road permit or special use permit for the road is issued to another person, or
(c) the road is declared a forest service road under section 115 (5) of the Forest Act.
(2) Any maintenance carried out under subsection (1) must be done in accordance with
the requirements of
- (a) a forest stewardship plan, and
(b) the Act and regulations.
(3) The district manager may require a person other than the licensee, who holds a
permit that authorizes use of a road in the Stillwater area, to assume all or part of the
responsibility for maintaining the road.
|